D. Bronwhyn Simmons

Sociétaire | Calgary

403.298.2403

Portrait de Bronwhyn Simmons
Affichage de 1 à 10 sur 15

Entrée en vigueur de la Loi fédérale sur le paiement rapide des travaux de construction

La Loi fédérale sur le paiement rapide des travaux de construction[1] (« Loi ») est entrée en vigueur le 9 décembre 2023. Celle-ci a pour objet de promouvoir la réalisation ordonnée et en temps opportun des projets de construction portant sur des immeubles ou […]

Plus

( Disponible en anglais seulement )

Construction estimates and consumer protection legislation

A recent case from Ontario has established that consumer protection legislation applies to consumer construction contracts in that province. The case, which is discussed below, is not an appellate case and as such is not binding on Alberta courts. However, […]

Plus

( Disponible en anglais seulement )

Justice will be swift: Alberta’s new streamlined trial process

The Alberta Court of King’s Bench recently announced that as of January 1, 2024, a new streamlined trial procedure for civil and family matters will come into effect.[1] This new “streamlined trial” format has the potential to resolve actions more […]

Plus

L’importance de suivre « l’approche standard » en matière de privilèges de la construction

Dans la récente décision Avli BRC Developments Inc. v. BMP Construction Management Ltd., 2023 ABCA 147, la Cour d’appel de l’Alberta a confirmé la validité de privilèges inscrits par des sous-traitants, laquelle était contestée en raison d’irrégularités lors de l’enregistrement. Contexte […]

Plus

« Ah! Ah! Vous auriez dû être plus prudent! » ne constitue pas un argument de défense dans une poursuite pour fraude

Depuis plus de 150 ans, la loi indique clairement que toute personne poursuivie pour fraude ne peut invoquer une défense fondée sur l’« absence de diligence raisonnable » ou la « négligence de la victime[1] ». Malgré les nombreux précédents, les parties défenderesses tentent […]

Plus

( Disponible en anglais seulement )

Alberta Court of King’s Bench reaffirms corporate veil test in the construction context

In the 2022 case, Parks v McAvoy, 2022 ABQB 294, the Alberta Court of Queen’s Bench (as it then was) evaluated whether a general contracting company’s director could be personally liable for damages when that director had performed work on […]

Plus

( Disponible en anglais seulement )

Alberta’s new prompt payment and construction lien legislation: An overview

On August 29, 2022, the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (the “Act”), came into force in Alberta. The construction lawyers at Miller Thomson LLP have been preparing for the Act’s implementation for over a year […]

Plus

( Disponible en anglais seulement )

Graham Construction and Engineering Inc v Alberta (Infrastructure): Is Strict Compliance Necessary for a Claim Under the Alberta Public Works Act?

The Alberta Court of Queen’s Bench clarified the requirements for perfecting a claim under Alberta’s Public Works Act, RSA 2000, c P-46 (the “PWA”) in Graham Construction and Engineering Inc v Alberta (Infrastructure), 2021 ABQB 184 [Graham]. This case arose […]

Plus

( Disponible en anglais seulement )

Zerbin v Vrbanek, 2021 ABCA 317: The Alberta Court kicks back at a contractor taking kickbacks

In the Alberta Court of Appeal decision, Zerbin v Vrbanek, 2021 ABCA 317 (“Zerbin”), and the preceding trial decision (Zerbin v Vrbanek, 2020 ABQB 797), the Alberta Courts assessed damages against a general contractor who was bleeding the owners on […]

Plus

( Disponible en anglais seulement )

How long is too long? The dismissal for delay test under Alberta’s Builders’ Lien Act

1361556 Alberta Ltd v Ristorante Cosa Nostra Inc, 2021 ABQB 157 In 1361556 Alberta Ltd v Ristorante Cosa Nostra Inc, 2021 ABQB 157 [Cosa Nostra], the Court of Queen’s Bench of Alberta addressed the test for dismissal for delay under […]

Plus

Affichage de 1 à 10 sur 15