Court denies validity of claim of lien but awards damages in unjust enrichment
The British Columbia Supreme Court recently considered whether a subcontractor’s claim of a builders lien was registered within the prescribed time limits in British Columbia’s Builders Lien Act, SBC 1997, c 45 (the “Builders Lien Act”). What makes this case...